Wednesday, December 8, 2010

Panels Set As Winter Sets In


Finally, all panels are set!

It seemed like a long time, but actually was only 17 days from delivery to setting the final panel. Between weather delays and working weekends to make up, we took about 12 full working days to finish.

As expected, the 8 x 24 roof panels were a handful. There were some tense moments. If their size alone wasn't enough we had a couple of complicating factors:
  • First, wet weather had made already soft ground around the site even worse. Operating the forklift was very difficult, as it sunk 1 to 2 feet in the muck when it had a load. The area around the site looks like we had a mud-truck competition. 
  • Second, the trusses we bought were constructed wrong. The height that they rose off of the wall plate was short, necessitating building up the wall plate, and the pitch, which was supposed to be 8/12 was wrong. It was actually somewhere around 7 7/8's or 15/16's, which meant that they were not as tall as a true 8/12 would be. This would not be a problem if the entire roof was supported by the trusses, but in this house that is not the case. Each end support is a SIP wall, which were a true 8/12 pitch and therefore ended up over an inch higher at the peak than the trusses. We had a choice, send the trusses back or compensate for the error in construction. Being late November and wanting badly to get under roof before bad weather set in we decided to go with what we had. It made installation a much more time consuming chore, but was preferable to waiting another week or more for new trusses. Turns out we made the right decision, as nasty winter weather moved in, and as of today remains.
Just before it started snowing we were able to get the conventionally framed roof on over the bedroom wing. We are now expecting a spell of single digit lows and highs in the teens. We need about a week of half decent weather to finish up details on the roofs so that we can get shingles on and dry everything out.

Windows and doors should be here in 3 days, and house wrap and installation will soon follow. Combined with a finished roof this should improve working conditions greatly. We are all curious to see how well the little 80K BTU propane heater we have will heat up the house!

No comments:

Post a Comment